  1. What are the advantages and disadvantages of waterfall model? Explain five Improvements for Waterfall Model to Work. (10 Marks)
  2. What is software Economics? Explain about the discipline and factors affecting software Economics showing the relationship. (10 Marks)
  3. Describe Model based software Architecture. Explain lifecycle phases of software Project Management. (10 Marks)
  4. What is Artifact sets and why is it essential? Explain different Artifact sets involved in Unified Process. (10 Marks)
  5. What is WBS and Why is it essential in project Management? Explain Line of Business Organization with different Roles and Responsibilities. (10 Marks)
  6. What is iterative process planning? Explain different planning guidelines and cost and Schedule Estimating process. (10 Marks)
  7. What are different levels of automation? Explain Process Automation along with 4 important Environment Disciplines. (10 Marks)
  8. Explain about Seven Core metrics. Elaborate about the different software management best practices? (10 Marks)
  9. Explain lifecycle expectation along with process discrimination and its parameters. (10 Marks)
  10. Explain Continuous Intergration. What is early risk resolution and why is it required? (10 Marks)